Section 1 vs Section 2 on a California Termite Report

If you work in Orange County real estate, you’ve seen it on almost every termite report: findings sorted into Section 1 and Section 2. The labels drive a lot of the conversation in escrow, so it helps to know exactly what they mean, where they come from, and what they don’t decide. This guide walks through how a California Wood Destroying Pests and Organisms Inspection Report is organized, using the definitions printed on our own Bugmasters reports.

Where the Section 1 and Section 2 labels come from

In California, termite inspections are regulated by the Structural Pest Control Board (SPCB), and the report format follows the Structural Pest Control Act. A “separated report” splits findings into categories so everyone in the transaction can see which items are active problems and which are conditions to watch. Bugmasters is licensed by the SPCB (SPCB #894), and our reports use the separated format.

On our reports, the definitions are printed right above the findings. Here they are in the report’s own words, lightly trimmed:

  • Section I: items where there is visible evidence of active infestation, infection or conditions that have resulted in or from infestation or infection.
  • Section II: conditions deemed likely to lead to infestation or infection but where no visible evidence of such was found.
  • Further inspection: recommendations to inspect areas which, during the original inspection, did not allow the inspector access to complete the inspection, and which cannot be defined as Section I or Section II.

That third category matters as much as the first two. We cover it in its own article on inaccessible areas and further inspection.

What Section 1 items usually look like

Section 1 is about evidence that’s there now. Common Section 1 findings include:

  • Evidence of drywood termite infestation, such as pellets (frass) or kick-out holes.
  • Evidence of subterranean termites, such as mud tubes.
  • Wood members damaged by termites.
  • Fungus (dry rot) damage to wood members.

Each finding is paired with a recommendation, for example fumigation or a local treatment for termites, or repair or replacement of damaged wood. Section 1 work is what a clearance is based on: once all Section 1 work is completed, we can issue a clearance. See what a termite clearance is for that part of the process.

What Section 2 items usually look like

Section 2 items are conditions, not damage. The inspector didn’t find visible evidence of infestation or infection, but the condition is likely to lead to it if left alone. Typical examples are things like wood touching soil, excessive moisture, or a plumbing leak where the wood is still sound. The same spot can move between sections: a leak with fungus damage under it is a Section 1 finding, while a leak with sound wood is a Section 2 condition.

How findings are numbered on a Bugmasters report

Agents and escrow officers often ask how to read the item list. On our reports, each finding has an item number and a letter, such as 7A, 8A or 11B. The number refers to the area of the property on the report diagram (for example attic spaces, the garage, or the exterior), and the letter separates multiple findings in the same area. Each item shows:

  • The finding: what the inspector saw.
  • The recommendation: what we recommend to correct it.
  • A price line for the estimate, or a note that it’s included with another item or unknown until further inspection.
  • The section tag, such as “(Section I)”.

Some drywood termite items also have a secondary recommendation, described on the report as a “secondary recommendation in lieu of fumigation.” That’s typically a chemical spot treatment with Termidor of the visible and accessible infestations only. The report states plainly that this is a sub-standard recommendation to fumigation, because concealed areas aren’t treated. Fumigation carries a three-year guarantee; chemical spot treatments carry a one-year guarantee. It’s there so the parties can choose, knowing the difference. Read more on termite spot treatment and fumigation.

At the end of the report there’s an approval page that lists each item with its primary estimate, any secondary estimate, and its section, so the work can be authorized item by item.

What the sections don’t decide

The report classifies findings. It doesn’t decide who pays for anything or what must be done before closing. Those questions are settled by the purchase agreement, the parties’ negotiations, and in some cases the lender’s requirements. We cover this in a separate article on who pays for the termite report and repairs.

General information, not legal advice. Your purchase agreement and escrow instructions control.

Tips for agents and escrow officers

  • Read the whole report, not just the summary boxes. The checked boxes on page one show which kinds of problems were found in accessible areas; the details and recommendations are in the item list.
  • Look for “further inspection” items early. An unknown price on an inaccessible area is an open question until someone opens it up.
  • Note primary vs secondary recommendations. If a secondary option is chosen, make sure everyone understands what it does and doesn’t cover.
  • Know what isn’t included. Our reports note, for example, that painting to match is not included in repair estimates, and that permits, if required, are the owner’s responsibility.
  • Check whether it’s a limited report. For a condo or a unit in a multi-unit building, a report may be limited to the individual unit; common areas and attached units aren’t included.

How Bugmasters handles inspections for a sale

Our inspections are free and take about 1 to 1.5 hours. Results come in 1 business day, and we email the report as a PDF to the agents and escrow officer you list. The owner doesn’t need to be home if we have access. Our inspectors aren’t on commission, so the report reflects what’s there. See our page for real estate agents and escrow, or the termite inspection overview. We serve Orange County’s 33 incorporated cities, from Anaheim to San Clemente.

If something on one of our reports isn’t clear, call us. Questions about a report should go to the company’s manager first, and the report also lists how to reach the Structural Pest Control Board. Ready to schedule? Request a free inspection.

Frequently asked questions

What is a Section 1 item on a termite report?

On our reports, Section I covers items with visible evidence of active infestation, infection, or conditions that have resulted in or from infestation or infection.

What is a Section 2 item?

Section II covers conditions deemed likely to lead to infestation or infection where no visible evidence of infestation was found.

What does further inspection mean?

It's a recommendation to inspect an area the inspector couldn't access during the original inspection. It can't be classified as Section I or Section II until it's inspected.

Does the report say who pays for Section 1 work?

No. The report classifies findings and recommends work. Who pays is decided by the purchase agreement and the parties.